Skip Navigation

thyssenkrupp Steel puts together largest investment package in 20 years

Production network in Ruhr area Duisburg, Bochum and Dortmund

By investing a high three-digit million euro sum, thyssenkrupp Steel is setting the course for the modernization of its production network at the Duisburg, Bochum, Dortmund and Andernach sites. The aim is to achieve higher-performance products, increased flexibility and greater customer proximity.

With this investment package, thyssenkrupp Steel is underpinning its claim to technology and quality leadership, and strengthening its position in the European market:

  • The expansion of the existing lines will go hand in hand with increased production capacity, which enhances delivery and schedule reliability.
  • The modernizations are part of the company's 20-30 strategy, which aims to focus more on profitable and growing markets arising, for example, from the energy turnaround and advancing electric mobility.
  • The focus is on high-quality steel grades which are required, among other things, for efficient electric mobility solutions in the area of motors and generators: powercore® Traction, for example. Products from the premium surfaces segment such as ZM Ecoprotect® and dual-phase steels, which are required above all for lightweight automotive construction in structural components and for crash-relevant components in the automotive sector, also continue to be of great importance.

The new and rebuilt facilities will enable thyssenkrupp Steel to optimally meet the changing needs of the market, e.g. demand for tighter tolerances as well as thinner and wider products. In principle, the investments in the production sites make an important contribution to the targeted climate-neutral steel production – and thus to the current transformation of thyssenkrupp Steel in general.

Duisburg site

Continuous casting line 4 & hot strip mill 4

At the Duisburg site, the former casting-rolling plant is being converted into a continuous casting plant with a downstream hot strip mill. The project is the largest single construction measure within the overall investment package. The casting-rolling plant in Bruckhausen has been shut down and partially dismantled since the end of October 2024 to make room for the new plant components. Up to 1,000 employees from thyssenkrupp Steel and partner companies are currently working on the construction site every day to erect the new buildings and units. The new continuous caster and the modernized hot strip mill will then go into trial operation and thus into ramp-up from May 2025. The slab warehouse will be put into operation before May 2025. The modernization will allow the plant's casting and rolling capacities to be increased and the capacity utilization of the upstream steel mill to be improved. In addition, the process-optimized plant technology based on Industry 4.0 solutions will allow the portfolio of ultra high-strength steels and premium surfaces to be expanded. Customers can expect significant quality improvements, more flexible slab production and lasting positive effects on their schedule and supply reliability.

Duisburg site

Investments in Duisburg

Continuous casting line 3

A new continuous caster is planned for Duisburg-Bruckhausen. It replaces continuous casting line 1 and will offer, among other things, significant metallurgical advantages which will be reflected for customers above all in increased productivity and improved surface qualities. The new line is planned to be completed in 2026.

Walking beam furnace 5

Walking beam furnace 5 in hot strip mill 2

In September 2022. the first slab passed through the new walking beam furnace in Duisburg hot strip mill 2. Since then, the state-of-the-art unit has been bringing up to 300 slabs per day to a uniform specified rolling temperature, in an energy-efficient manner, over an area of 54 meters. Different heating zones allow variable temperature control – in this way, the slabs can be provided in advance with special material properties. In addition, because the solid steel blocks are carried through the furnace and not pushed, as opposed to the previous technology, process-related scratches on the underside can be almost completely eliminated.

Walking beam furnace in hot strip mill 1

In December 2024, thyssenkrupp Steel modernized the walking beam furnace at the Duisburg-Bruckhausen site in hot strip mill (WBW) 1 to the highest technical standards. The key advantage of the overhauled unit is a further improvement in quality, particularly for electrical steel production, the basic material for the energy transition. With the modernized walking beam furnace, surface defects are already avoided when the slabs are reheated: The more homogeneous temperature distribution over the entire length of the slab leads to a reduction in temperature loss in the middle of the slab and at the same time to a reduction in so-called rail spots, the contact points of the slabs with the support tube system. In addition to the improved quality, the modernized furnace also sets new standards in terms of energy consumption and energy efficiency.

Smart weightlifter: Production processes will be synchronized in an innovative way with the new slab cranes

Slab storage yard

thyssenkrupp Steel has ordered a fully automated slab storage yard from Italian plant manufacturer Danieli & C. Officine Meccaniche for a mid-double-digit million euro sum. The most significant special feature of this project is its intelligent logistics control. This enables the real-time synchronization of around 1.7 million metric tons of slabs per year. Some of this is used directly from the continuous caster in the new hot-strip mill 4, or also fed from the new walking beam furnaces. In addition, there are plans for the installation of a warehouse management system which calculates the distribution of the slabs from various sources in real time and optimizes all crane movements.

In addition to the optimum usage of the 19,200 square meter slab storage facility, another advantage lies in improved operational safety, as there will in future be no need for personnel on the ground. The Danieli company is providing four fully automated slab cranes and taking on the construction and installation of the entire steel structure.

Bochum site

Double reversing stand

Double reversing stand

thyssenkrupp Steel is pressing ahead with the expansion of its plant on Essener Strasse in Bochum into a competence center for electromobility. An important milestone was reached in October 2022 with the laying of the foundation stone for a new double reversing stand, which was put into operation a year later. This unit, in which thyssenkrupp Steel has invested around 100 million euros, will be used to produce high-quality, non grain oriented electrical steel for use in highly efficient electric drives. The trend towards ever thinner and high-silicon materials places particularly high demands on cold rolling technology. The new rolling stand is capable of rolling particularly thin materials by means of a freely controllable number of forward and reverse rolling processes. Specifically, the new system can be used to produce non-grain-oriented electrical steel strip with high flatness and extremely tight tolerances in thicknesses between 0.20 millimetres and 0.50 millimetres. In addition, the double reversing stand is used to produce high-strength multiphase steels.

Annealing and isolating line

With the start-up of the new annealing and insulating line in January 2025, the modernization of the Bochum site is now largely complete. The modern and energy-efficient system enables the production of electrical sheets up to 0.2 millimetres thick with particularly homogeneous mechanical and magnetic properties. They are specially designed to meet the requirements of highly efficient motors, which are primarily used in electric vehicles. The rolling mill upstream of the annealing and insulating line, a double reversing stand installed on the basis of the latest technology, has already been completed. The two new units will be complemented by a new electrical steel strip inspection line and a finishing line that has now been commissioned to cut the finished sheets and assemble them for customers. The finishing line is scheduled to go into operation in 2027. In future, the new annealing and insulating line will be able to produce up to 200,000 tons of non grain oriented electrical steel per year.

Dortmund site

Investments in Dortmund

Hot-dip coating line 10

With the startup of the new hot-dip coating line (FBA 10) thyssenkrupp Steel has opened another chapter in the history of the future at its Dortmund location. The line, which is one of the most modern of its kind in the world, serves the increased demand for premium surfaces in wider dimensions. The line, which is around 350 meters long and up to 65 meters high, will in future produce materials for vehicle interior parts and outer panel applications in established hot-dip galvanizing as well as on a highly innovative zinc-magnesium basis, which allows both material and cost savings and is sustainable thanks to its low application thickness. The automotive industry in particular will benefit from the expanded production capacities of up to 600,000 metric tons of steel per year for hot-dip coated premium products from the new FBA 10.

Andernach site

Coating line 13

Coating line 13

In fall 2022 thyssenkrupp Rasselstein will start production of special chromium-plated packaging steel at the new coating line 13. The line uses innovative Trivalent Chromium Coating Technology (TCCT®) which is based on chromium(III) in the manufacturing process instead of the chromium(VI) previously used. Thus, the product manufactured on the line fully complies with the requirements of the EU REACH Regulation. The special chromium-plated packaging steel is typically used for the production of lids and bottoms for pet food cans, crown corks, printing ink cans and valve disks. The new coating line also enables the chrome-plating of even wider and thinner sheets.

Contact

ThyssenKrupp Contact

Mark Stagge

Head of Public & Media Relations, thyssenkrupp Steel Europe

Telephone: +49 203 52-25159

Fax: +49 203 52-25707

Send email
To the top